top of page
160 Bloor Street East
![]() | ![]() |
---|---|
![]() | ![]() |
![]() | ![]() |
![]() |
Project Description
​
Spring 2017
-
Entrance ramp Epoxy replacement
-
Concrete slab repairs
-
Polyurethane-methacrylate waterproofing system installation
-
Consultant: Stephenson Engineering Ltd
Summer 2015
-
Parking garage and loading dock Repairs
-
Concrete slab repairs
-
Heavy duty epoxy waterproofing installation
-
Steel plate installation
-
Trench Drain repairs
-
Interior leaking crack repairs
-
Foundation wall injection
-
Exterior walkway replacement
-
Consultant: Stephenson Engineering Ltd