Project Description 
​
Winter/Spring 2018 
  • Parking Garage and Exterior walkway repairs 
    • P1&P2 South elastomeric waterproofing/resurfacing  
    • Foundation wall water outlet installation
    • Exterior catch basin replacement
    • Hot applied waterproofing 
    • Foundation wall crystalline  
Consultant: Stephenson Engineering Ltd
​
​
Winter/Spring 2017 
  • Parking Garage and Exterior walkway repairs 
    • P1&P2 North elastomeric waterproofing/resurfacing  
    • Exterior expansion joint replacement
    • Slab on grade catch basin replacement
    • Exterior catch basin replacement
    • Hot applied waterproofing 
    • Foundation wall crystalline
    • Drainage pipe installation  
Consultant: Stephenson Engineering Ltd
​
​
Spring 2016
  • Tunnel Leak repairs 
    • Tunnel crystalline 
    • Interior walkway trench drain installation
    • Tile replacement
    • Sump pump installation
Consultant: Stephenson Engineering Ltd
​
​
Winter 2015
  • Parking garage repairs 
    • P1&P2 South elastomeric waterproofing/resurfacing 
    • Mechanical expansion joint replacement
    • Drain replacement 
Consultant: Stephenson Engineering Ltd
​
​
Summer 2015
  • Ramp trench drain repairs 
    • Concrete repairs
    • Ramp trench drain waterproofing and topping installation
    • Heated re-bar repairs 
Consultant: Stephenson Engineering Ltd